The screw with the fish pass to the right and the engine house above - now almost completed.
THNM hosted some visitors on Friday from Bollington who are considering a similar scheme, they were very impressed on the progress made so far.
The screw with the fish pass to the right and the engine house above - now almost completed.
THNM hosted some visitors on Friday from Bollington who are considering a similar scheme, they were very impressed on the progress made so far.
Taken last week before the roof was completed - also below Chris in hard hat looking pensively at the sluice gate before it got to its resting position.
Further clearing of the intake has taken place in readiness for the commissioning tests on the screw later in the month.
A view of the screw taken from the engine house looking towards the stone arch at the end of the tail race - note the deflectors now in place on the right hand side.
Well a change in the weather in the past 48 hours has made a welcome change for everyone.
A good week for progress, especially tasks that although they may not take a large amount of time to complete they are in themselves often a culmination of weeks of effort - for example removing the spacers from the screw and actually seeing it turn properly for the first time (albeit manually for the time being). The engine house continues to make steady progress and already looks like it was part of the original mill buildings and will be finished off with a nice slate roof. Also this week the sluice at the top end of the screw has been lifted into position, this will be controlled automatically and will be lowered to adjust water levels into the screw.
Next week work will continue on clearing and concreting the intake area and the build on the engine house.
Pictures to follow...
Vorsprung durch Technik
Chris and Yvette of Western Renewable Energy
The start of a new month is as good a time as any to review what we have achieved in such a short period of time and to briefly review the remaining activities that lie ahead prior to commissioning.
Looking at our project plan to date we can see we are very much on target - key activities in June were to meet the deadline for turbine delivery (The Big Lift) and initial location onto site and once in situ to pour the concrete slab that the gearbox and generator will mounted on. The setting of the slab itself was very much time critical needing 14 days to set before anything could be safely mounted onto it.
Activities planned for the next week are centred around completion of the fish pass work by mortaring the aluminium sections into place and concreting the sides and continuing the build of the magnificent archway at the bottom end of the turbine.
Details of the THNM Ltd AGM and official opening will also be announced in the next few days.