Thursday 29 May 2008

Eleven days until The Big Lift - (29/05)

The last of the shuttering safely being lifted



With only 11 days left until The Big Lift the site preparation continues at a pace.


The last of the shuttering which moulded the concrete walls has been removed, cleaned and oiled. Soil is being back filled into the area between the concrete wall and the original picnic area.


The journey for the screw will start next Monday (2 June) with transport leaving the UK to collect the screw from Germany - we will try and plot its journey across Europe on this blog.


Soil being backfilled against the concrete wall

No comments: