Monday 31 March 2008

Preparation work - (31/03)

Ground height being reduced in line of the original United Utilies storm overflow pipe









Filling the dumper - the spoil is then either taken off site or some will be re-used to cover the re-routed United Utilities storm pipe






Wall removal, for ease of access later with the turbine - all stone is being stored for later re-use within the project.






Spoil storage area on the 'safe' side of the weak bridge - it is then collected from here for disposal



A view of the emerging (presumed) leat into the wheel pit area prior to the move of the United Utilities storm pipe.

No comments: