Many of you not local to New Mills have been asking to see footage of the screw in action - well here it is courtesy of our very own local Steven Spielberg Ken !
Monday, 15 September 2008
The screw in action - (15/09)
Thursday, 11 September 2008
Messing about in the river... (11/09)
The original Torr Mill on the site of Torrs HydroOver the past two days Sean and Till (two of the Directors of Torrs Hydro New Mills) have been up to chests in water removing the debris which improves the flow of water to the screw and in doing so increased the output of electricity to the New Mills Co-op.
Its not expected that this activity will become a regular occurrence, but next time it does we will be asking local volunteers for assistance to speed the process up - so be prepared to get your feet wet !
Wednesday, 10 September 2008
Ten thousand hits ! - (10/09)
Tuesday, 9 September 2008
The rain came down... (09/09)
Friday, 5 September 2008
Torrs Hydro New Mills - (06/09)
Bit of education for any fellow geeks out there :
A Megawatt-hour (MWh) is : 1 megawatt acting over a period of 1 hour. One megawatt-hour is equal to 1,000 kilowatt-hours or 1 million watt-hours. The primary difference between a megawatt and a megawatt-hour is that “megawatt” measures the capacity of an electric generator and “megawatt-hour” measures the actual amount of electricity it produces over a certain period of time.
Thursday, 4 September 2008
Invitation from Water Power Enterprises - (02/09)
You are warmly invited to the launch of Settle Hydro's Share Offer on Saturday 6 September, 10am, at Victoria Hall, Settle. Settle Hydro Ltd - a development of Settle Area Regeneration Team, StART, Settle District Chamber of Trade and Settle District Going Green - plans to install a 50kW hydro power plant at Bridge End Weir, in Settle. The plant would be Yorkshire's first community-owned and surplus monies from the sale of hydro electricity would fund local environmental and community projects. The share offer gives individuals, local businesses and social investors the chance to become members of a ground breaking renewable electricity project that will provide clean, green electricity. It's a unique way to demonstrate a commitment to a sustainable environmental project.
Sunday, 31 August 2008
Torrs Hydro in action - (31/08)
As we approach the handover of Torrs Hydro New Mills from project into production, all the hard work is just about completed, commissioning has been successful to date and the Archimedes screw has connectivity to the New Mills Co-op and the National Grid.
The picture below shows the screw running at approximately 30% of capacity - this is governed automatically by the river level with the sluice gate being adjusted to ensure that an agreed level of water goes over the weir - the more water (not unusual for New Mills) the more electricity is produced.
Also a quick glimpse inside the control room of Torrs Hydro - its hardly Star Trek, but the control systems ensure the correct amount of water is flowing at all times and will automatically shut down the screw and sluice gate if a problem should ever arise.