Wednesday, 2 July 2008
Where does all that energy come from ? - (02/07)
Tuesday, 1 July 2008
Project update - (01/07)
The start of a new month is as good a time as any to review what we have achieved in such a short period of time and to briefly review the remaining activities that lie ahead prior to commissioning.
Looking at our project plan to date we can see we are very much on target - key activities in June were to meet the deadline for turbine delivery (The Big Lift) and initial location onto site and once in situ to pour the concrete slab that the gearbox and generator will mounted on. The setting of the slab itself was very much time critical needing 14 days to set before anything could be safely mounted onto it.
Activities planned for the next week are centred around completion of the fish pass work by mortaring the aluminium sections into place and concreting the sides and continuing the build of the magnificent archway at the bottom end of the turbine.
Details of the THNM Ltd AGM and official opening will also be announced in the next few days.
Thursday, 26 June 2008
Strong lads - (26/06)
Wednesday, 25 June 2008
Thats a lot of water in that river ! - (25/06)
A somewhat bizarre picture with a flying JCB and workforce with heads poking out of the water.

Carefully being moved into position the frame for the stone archway.
My thanks go to Alan Jennings for these great pictures.
Tuesday, 24 June 2008
Into the river we go - (24/06)
At this stage of the project it was time to open up the tail race out into the main river by breaking through the existing mill wall that had retained the river for the past 150 years. This in itself brings challenges as two diggers had to be lowered into the River Goyt (suitably above water to ensure environment agency guidelines are maintained) and then a process of removing years of debris and ensuring the correct depth for the exit.