Wednesday, 2 July 2008

Where does all that energy come from ? - (02/07)


The Torrs Hydro New Mills Archimedes screw will be fed from just above the Torr weir on the Rover Goyt, just a few metres after it has been met by the Rover Sett.

Theres a lot of water in the River Goyt and theres a lot of water needed to turn our screw.

The current local measuring station for the Goyt is at Marple Bridge and was installed in 1969.

Since then 3.8 million million (3.8 x 10 ^12 or 3,800,000,000,000) litres of water have flowed over Torrs weir.

Summer of '76 - the minimum daily amount was on 26th August 1976 when 29,548,800 litres flowed over in one day.

Winter of '91 - and the most was on 21st December 1991 when 5,158,080,000 litres sloshed over the weir crest.

Tuesday, 1 July 2008

Project update - (01/07)

The start of a new month is as good a time as any to review what we have achieved in such a short period of time and to briefly review the remaining activities that lie ahead prior to commissioning.

Looking at our project plan to date we can see we are very much on target - key activities in June were to meet the deadline for turbine delivery (The Big Lift) and initial location onto site and once in situ to pour the concrete slab that the gearbox and generator will mounted on. The setting of the slab itself was very much time critical needing 14 days to set before anything could be safely mounted onto it.

Activities planned for the next week are centred around completion of the fish pass work by mortaring the aluminium sections into place and concreting the sides and continuing the build of the magnificent archway at the bottom end of the turbine.

Details of the THNM Ltd AGM and official opening will also be announced in the next few days.

Thursday, 26 June 2008

Strong lads - (26/06)


Another great picture courtesy of Alan Jennings - just goes to show how 'strong' the construction team are working down on the Torrs Hydro project.

Wednesday, 25 June 2008

Thats a lot of water in that river ! - (25/06)

A somewhat bizarre picture with a flying JCB and workforce with heads poking out of the water.


I know its stating the obvious but since breaking through the river wall at the bottom end of the turbine there sure is a lot of water about !

Now the debris has been cleared and the depth of the channel is correct a new 'stronger' coffer dam will have to be put in place to hold back the millions of litres of water that crash over the Torr weir each day - and thats a whole lot of water to hold back !

Next on the jobs to be done this week include starting to build the exit archway (this will look like a masterpiece when completed) and to concrete the fish pass so that the aluminium ladder can be put in pace to allow our trout and salmon to head up river towards Hayfield on the Sett or towards Whaley Bridge on the Goyt.



Carefully being moved into position the frame for the stone archway.

My thanks go to Alan Jennings for these great pictures.

Tuesday, 24 June 2008

Into the river we go - (24/06)


At this stage of the project it was time to open up the tail race out into the main river by breaking through the existing mill wall that had retained the river for the past 150 years. This in itself brings challenges as two diggers had to be lowered into the River Goyt (suitably above water to ensure environment agency guidelines are maintained) and then a process of removing years of debris and ensuring the correct depth for the exit.







Welcome to The Mersey Basin Trust - (24/06)


Last week Torrs Hydro New Mills played host to a group from The Mersey Basin Trust, after a brief tour of The New Mills Heritage Centre we came down to have a project overview with WRE whilst basking in the glorious New Mills weather - we look forward to hopefully working more closely with them in the future.

Some more Big Lift pics.... - (24/06)


Courtesy of Jeanne Daniels.