Sunday, 8 June 2008

'Eureka' we've found it ! - (08/06)

Gently does it as 12 tonnes slowly descends into the Torrs


What a great day - perfect weather, a great turn out by New Mills for the 8:30am start and no screw in sight !

Eventually after finally locating our driver - who had taken a very scenic route to New Mills we started the long awaited lift of the Archimedes screw down towards its new home in the Torrs.

With excellent work by Ainscoughs cranes and Western Renewable Energy a perfect landing was guaranteed - we even made the tea time Granada news !



The crowds gather (again) to watch in anticipation









Tilly wonders 'why so many Bob the Builders ?'








Saturday, 7 June 2008

The Big Lift - (07/06)


Well its taken almost 18 months to get to where we are today.

A long journey which will over the next few weeks give our town of New Mills a unique place in renewable energy history.

But for now lets concentrate on an important milestone within the project - the lowering of the Archimedes screw from the Union Road bridge down into the Torrs.

The weather is set to be nice and sunny so grab your camera and go watch a piece of history in the making - remember 8:30am Sunday 8 June.

Friday, 6 June 2008

Two - (06/06)

Just two days and counting - Well the screw arrived safely from Germany on Wednesday and is being stored and will be transported by road to Union Road to arrive in good time to be lifted down into the Torrs on Sunday morning.

The big task today was to carry on working on building the piles of railway sleepers and the creation of the ramp which some time next week will allow the screw to be moved to its final resting place.

Normally this would be done via a large crane, but due to weight restrictions on the bridge into the Torrs we have had to resort to more 'traditional' methods of moving 11 tonnes of steel - it will be slowly wheeled on its giant go-kart towards the concrete pit as I like to call it - this is about 10 feet deep but has been made level at the top end with ground level to allow the screw to be wheeled into position where it will then be held by an A frame whilst one pile of sleepers is removed then allowed it to be slowly manoevred by heavy duty winches that have been bolted to the concrete floor.
Below we can see some of teh 150 plus railway sleepers that have been used - each one has had to be craned into place and then takes two men (or women Yvette) manoevre into the final position.


Heavy duty winches that will be used to manoevre the crew


The ramps start to take shape





Three - (05/06)


With less than three days to go before the arrival of the Archimedes screw key final preparation become a priority - the clearing of the area that the screw will rest in once it is lifted down from the Union Road bridge, levelling the entrance to the Torrs Hydro site, the creation of what looks like a giant go kart that the screw will be lowered onto to enable it to be safely moved into position over the next week - all key tasks and all completed so we're just about ready to go.


Below we see the cradle part assembled and also being transported to temporarily live beneath Union Road bridge until Sunday.






Tuesday, 3 June 2008

Four - (04/06)


Just four days until The Big Lift and our Archimedes screw has passed through Germany and is carefully making its was across France/Belgium to be shipped across the channel to head North towards New Mills.

In the picture below Sean from Construction Projects, (who have been performing wonders on renewing the existing stonework on the river wall is on the scaffold.


The Turbine outfall is being worked on here, making use of the good access provided by the concrete trough -this will allow a digger to get in and work in the river below the weir- which is usually very inaccessible due to the river being bordered with high retaining walls all through the Torrs. This opportunity will be lost once the turbine arrives on Sunday, so it is a high priority to finish this particular work by Saturday.

This will involve further removal of bedrock to dig out into the river bed, to give a smooth exit to the water and allow maximum power to be derived from the turbine. The construction of the stone arched outfall using original stone will occur after the turbine moves to its final position, the wooden former for the arch was shown earlier on the blog - it's has been christened the 'pig ark' for the time being.


Five - (03/06)


With the screw now secured to the HGV, the route back to the UK planned and site preparation continuing as the big day looms even closer we start to look at the big day itself

Volunteer Marshall's were briefed at the Town Hall last night and everything is coming into position for Sundays Big Lift.


Later in the week we will post a list of good vantage positions to watch the lift from but for now here's brief itinerary for Sunday :


7.30am Road Closure at Union Road Bridge - no access to public
8.00am Ainscough Crane arrives at Union Road Bridge
8.30am Archimedean Screw arrives
9.00am Ainscough Crane starts Big Lift
9.30am Ainscough Crane leaves
9.30am Union Road re-opens



Later this week the remaining shuttering will be collected and the fish pass will be assembled.

Six - (02/06)


Six days and counting.

A great turn out tonight at New Mills Town Hall to discuss what the volunteer Marshall's would need to do next Sunday morning - many thanks to all who gave up their time and don't forget to set your alarm clocks for Sunday morning !


The journey to collect our screw began today with the haulage company starting the long road journey to Germany to safely collect and deliver in time for next Sundays Big Lift