Wednesday, 21 May 2008

Its pouring down - (21/05)

From mixer to pump to Torrs Hydro New Mills

...No not the rain, but the concrete. Ideal weather for the last two days has seen hefty progress as the concrete has been pumped across the river into the shuttered wall cavities.

At times gravity seemed to want to take the concrete to places it didn't need to be but now thanks to Chris, Yvette and the team we are left with four walls that are now hardening waiting to appear once the shuttering is taken off tomorrow and Friday.

Monday, 19 May 2008

The week for walls - (19/05)


Such a hectic week for the project - the shuttering is all but completed and the concrete for the walls will be poured Tuesday and Wednesday.


After this the shuttering will be dismantled (easier than assembly) on Thursday and Friday to reveal four newly created walls that will house the Archimedes screw.

Wednesday, 14 May 2008

Giant Meccano with fish and chips - (14/5)

No longer an artists impression - part of the rebuilt river wall.



Yesterday I spent another day working with the Chris, Yvette and the team down at the Torrs Hydro yesterday and great fun it was too - but hard work for an office type like me !

Main job for the day was continuing to build the shuttering which will enable the concrete to be poured to build the side walls of our concrete bunker.


The shuttering is very much like a giant Meccano kit but takes tow people to lift and manoeuvre each section and then fits together with various clamps, pins and other heavy duty bits and pieces - its then all drilled into the concrete base to ensure that when the concrete is poured we end up with a perfectly straight wall that matches the original drawings.

We worked that hard in the morning that a 'Crispy Cod' fish and chip lunch was just what the doctor ordered to sustain us through the afternoon.

Home sweet home - site base for the Torrs Hydro team.

Top view of the shuttering

The gap between the shuttering which will soon become a reinforced concrete wall.

Drilling the supporting props into the concrete base.

Props, scaffolding, clamps and other assorted Meccano !

The inside of the bunker soon to house the Archimedes screw

Monday, 12 May 2008

Torrs Hydro needs you ! - (11/05)


With the base concrete now set and the shuttering for the side walls growing by the hour we are approaching the critical stage of the project 'The Big Lift'.

Whilst the finer points of the day are being covered by the various contractors and authorities we do need a number of volunteers to assist on the day - we are looking for local volunteers who are willing to be stewards on the day - a large crowd is expected.

We don’t know all the details yet, but the lift day is Sunday 8th June, the time is not confirmed yet (assume around lunchtime).


Please let us know if you are interested in helping you can leave a message on this blog or email us at secretary@torrshydro.co.uk . You can pass this invitation to friends but they must be 18 or older to help.

A meeting for all volunteer stewards will be held at 6:00pm on Monday 2nd June at New Mills Town Hall.

Tuesday, 6 May 2008

Video footage - (06/05)

Some more footage of the site taken last Friday and shows the finished concrete base - in total some 200 tonnes of concrete were poured and tamped down and some 800 tonnes of soil, stone and rock were removed.

Five weeks and counting... (05/05)




Just less than five weeks to go till "The Big Lift" (8 June) and work is now moving at a tremendous pace, the concrete base is in and side walls are now under way - hopefully this weeks fantastic weather will continue.


We now have a company logo (see above) which I'm sure you'll all agree looks fantastic - this will be used on all future share holder communcations, share certificates.

Friday, 2 May 2008

A bit of the hard stuff ! - (02/05)

Concrete ready for pouring


...Concrete , not whiskey (although we will be celebrating the arrival of our Archimedes screw in due course).

The last couple of days has seen a remarkable transformation of the site from what was at times a muddy quagmire to a crisp and clean concrete lined bunker (for want of a better description).

Over Thursday and Friday approximately 200 tonnes of concrete was delivered and transported from the mixer, down the wooden chute and man handled into position around the supporting metal frame work to make the base for the Archimedes screw and generator.
Once poured the team have to work quickly to get it into the correct places.

The old and the new - newly layed concrete nestling in Torr Mills foundations